현장시공순서

  • 제작공정
  • 현장시공 순서
  • 컨설팅/견적문의
  • 주문절차 안내
시공계획 수립→반입→앙증→설치→배근→검수→콘크리트 타설
Construction planning Establishment of construction plans
- Overview, importing plan, process planning, safety management planning
Be cautious about the difference in structure type
Importing Planning of equipment, importing path,
  material inspection method


Pile up by slippers according to the site plan
In case of piling up at working point
: simultaneous imports and hoist
Hoisting Preparation for Hoisting – cleaning, marking, components preparation
Hoisting by slippers according to the site plan
Installation Installation in accordance with the site plant
- Use of beam part
- When overlapping part is damaged during transport or
  hoisting, immediate correction is required for construction
- nstallation of the first sheet according to baseline
- After installing the first Superdeck, temporarily fix the platform
- Installation of Superdeck sequentially
- Interlock the overlapping parts
- Finish the installation using a side-panel or Flashing
- Fix the platform of Superdeck
- Recovery of slippers
SR group
: Be cautious about the position of CRANK
  Nailing of plate into the platform (@300)


S group
: Be cautious about to secure the length of extension of Supderdeck
  Welding the Straight-rod to platform (@200)
Arrangement Arrangement of Connecting bars
Arrangement of Lower Distribution bars (2 ways for Slab)
Arrangement of components
Arrangement of Upper Distributing bars
Arrangement of Reinforcing bars
Inspection Inspection of installation state
Inspection of arrangement state
Check for Sheath thickness
Supplement of inadequacy
Concrete placing Production of high-quality slab